Basic Operations
Alarm Muting Cleaning Fan Filter Using Orderwire Phone Analyzing and Testing Optical Spectrum Plugging/Unplugging patch cord
Page 3
Alarm Muting
Step 1
Operation Check the MUTE switch on the cabinet, which shall be ON normally. Set the switch to OFF and the alarm sound stops. Check the ALC switch on SCC, which shall be ON normally. After confirming an alarm, set the switch to OFF and the alarm sound stops. If alarms are connected externally to the centralized alarming system, check if the switches and connection cables on the centralized alarm system are normal.
Page 4
Step 1
Operation Draw out the air filter by the handle. Take the air filter outdoors and wash it, then mop it and have it blown to dry at a place with good ventilation.
1. Fan (6 PCS)
2. Air filter
3. Handle
After cleanup, insert the air filter back. Align the air filter to the guide rail on the lower part of the subrack, and push it in gently.
5.Alarm indicator
6. Connector
Page 5
Page 6
Set the spectrum analyzer to the WDM test mode. Test the indices of each channel of signal and record the result. Compare the result with history or standard data, and then analyze the exceptional data.
ALM
MON
Spectrum analyzer
Page 7
Plug/unplug SC/PC: use special tool (such as fiber extractor) Plug/unplug LC/PC: in the axial direction without rotation
Plugging/Unplugging Card
No Fiber Connected
Plugging: ABC
C
Unplugging :DE
D
HUAWEI TECHNOLOGIES CO., LTD.
E
All rights reserved Page 9
Replacing Card
Make sure the board to be replaced and the replacement board are the same board type, especial for OTU cards. For example: SSE1OAU01
Board type ID SSE1OAU01
Handle bar
Card
Page 10
Replacing Card
special attention: Before replacement, configure the ID After replacement, resend the configuration data to NE from NMS
Page 11
Replacing Card
Check board version
Skilled at the operation methods in General precautions. The setting of board jumpers and DIP switches; Input optical power range of optical interface board;
Remove the optical fiber from the front panel; Width of the front panel.
During replacement
Wear an ESD wrist strap. Correctly swap the board. Avoid short-circuit of the board. Check whether the board is working normally, and upload configuration on the NM again.
After replacement
If you replace the SCC board, you should upload the original SCC configuration data to the NM, and then download them from the NM to the new SCC. Pay attention to NE user configuration.
Page 12
OTU
For new OTU: a. The type is identical with the original one. b. The wavelength, optical module is identical with that of the original one. a. Prevent the over-high input optical power from damaging optical components. b. Keep the operating band of the new optical amplifier unit identical with that of the original one. c. Do not stare into the output optical interface, since the output optical power of OA is very high. a. Prevent the over-high input optical power from damaging optical components. b. Keep the operating band of the new optical amplifier unit identical with that of the original one. c. Keep the type of the substitute board identical with that of the original one. a. The type of the substitute board is identical with that of the original one and whether it supports LHP system application. b. The input optical power All rights reserved Page 13
OA
Optical multiplexing/demul tiplexing & add/drop multiplexing unit Optical supervisory channel unit
MUX/DEMU X
Page 14
Resetting Board
Methods:
SCC
RST Button
RUN ALM ETN
RST
ALC
Page 15
DISPLAY
OUT/Tx
CONTROL BOARD
TEST INTERFACE
MON
Offline test
Connect power meter to OUT/Tx port
2 3
OTU
Attenuator
Page 18
Page 19
Daily
Monthly
Check the fan tray assembly and clean the air filter Check the orderwire phone Test bit error rate (BER)
Quarterly
Test optical signal-to-noise ratio (OSNR) at main path interface at the receiver (MPI-R) Test OSNR at main path interface at the transmitter (MPI-S) Check the cleanness of cabinet
Yearly
Page 20
Environment
Power - 48V (-38.4 ~ -57.6V ) Reliable Grounding
Equipment name
Temperature
Long-term running Short-term running -5C 45C
Relative humidity
Long-term running 10% 90% Short-term running 5% 95%
0C 40C
Note: The temperature and humidity are measured at 1.5 m above the floor and 0.4 m in front of the equipment. Short term means that the successive working time does not exceed 72 hours and the accumulated time every year does not exceed 15 days.
Red
Indicator
Critical
alarm indicator
The equipment The equipment has a critical alarm, does not have any which is accompanied critical alarm by the audio alarm The equipment has The equipment a major alarm does not have any major alarm Current power supply of equipment is normal
All rights reserved
Yellow
Indicator Green indicator
Major alarm
indicator Power Indicator
Loading programs
Running normally No alarm Minor alarm Major alarm Critical alarm Called by an orderwire phone
On
Off On Flashing
Page 23
Off Flashing three times every other second Flashing twice every other second Flashing once every other second On
Page 24
Summary