Professional Documents
Culture Documents
P
SELF-SHORING SYSTEM
wL- P
2 wL- P
2
SELF-SHORING SYSTEM
Let k wL
2 tan EI
where P
wL
2 kL
dk L k cos(kx) k sin(kx) tan
2 2
2
1
M EIv '' 2 2k 2k cos(kx)
2 2
2k L
2 2 kL kL tan
k sec kL 2sin sin( kx )
2 2
SELF SHORING SYSTEM
Therefore, P = w L
Where = 0.40 and w = total service load during construction
Or, = 0.25 and w = total service load during use
P is greater of these two values
: Construction
: Removal of P
Removal of force P
SELF-SHORING SYSTEM
Lateral
Plastic Moment Axial Load
Phase of Construction Deflection Torsional
Capacity Capacity
Buckling Check
Pre-Composite - no
Stage I: Construction
loads
yes yes yes yes
concrete
Pre-Composite
Stage II: Concrete-
loads yes yes no yes
concrete
Removal
Stage of Selfof
III: Removal
yes yes no yes
Shores
force P
Stage IV: Structure
Composite Phasein yes yes no no
use
SELF-SHORING SYSTEM
Construction Stage
In this case the value of the counterbalancing force P and the beam
For 8 ft. spacing - beam is W8 x 31 - force P is 6.3 kips
For 10 ft. spacing - beam is W8 x 35 - force P is 7.9 kips
The overall depth of the floor system after construction will be 13
in. and 15 in. for 8 ft. and 10 ft. spacing respectively.
TURNBUCKLE
Threaded Rods
Torque the turnbuckle-threaded rods
connection until the desired
displacement at midspan is achieved
SYSTEM TWO: SCREW JACK SYSTEM
SELF SHORING SYSTEM
b >4% requires
20 45 3.5 20 45 46
8 30 45 3.75 8 30 45 127
40 45 4 40 45 300
stiffer beams be
20 45 3.5 20 45 70
10 30 45 4.25 10 30 45 145 used
40 45 4 40 45 345
SELF SHORING SYSTEM
Fire resistance
Recent move in European countries towards eliminating fire
proofing for floor beams based on Cardington fire tests
Requires anchored reinforcement to develop cable action in
concrete slab
Using AISC Design guide 19 we find that there is a need to
fire protect the steel deck or use light-weight concrete
More detailed evaluations are being conducted
TYPE A CANDIDATE
SELF SHORING SYSTEM
FIRE RESISTANCE
SFRM Solution
- Based on current code, SFRM or Gypsum board fire
protection would be required
Gypsum Board Solution
SELF SHORING SYSTEM
Other comments/recommendations
- System is most efficient for spans between 20 30 ft, recommended maximum
span is 30 ft
- Specific W sections tailor made for system could be designed and implemented
- Implementation in laboratory is pending
- Experimental validation of stiffness, strength, fire resistance, and floor vibration
limits
Self-Shored System
- Implementation in a real structure Technological Feasibility Economical
Merit Merit Merit
9 9 10
8 6 5
8 9 9
9 8 9
9 7 7
7 7 6
8 8 8
7 7 6
5 10 6
ASSUMED LAYOUT
DSC Design 30 ft Span
CROSS SECTION
NOTE: STAGGERED STUD SPACING MAY
BE NEEDED BASED ON MAXIMUM AGG.
SIZE
DISCUSSION
- Profiled system is an alternative to flat face DSC system
- System maintains a shallow overall depth, although slightly
deeper then flat face DSC system
- Overall increase in weight, however performs better from floor
vibration standpoint
- Uses existing cellular deck profiles
- Side-lap connections on deck may inhibit casting of concrete
- Determining how interface shear the profiles can transfer needs
to be determined
DSC Systems
Overall Conclusions
- Present merit as candidates for long span slab systems in steel MSR
- Main issues corresponding to the systems is in their fabrication and
related costs
- It was concluded by committee that at this time, the DSC systems may
likely not be feasible for current implementation
- Committee ratings areEconomical
summarized below
Double Skin Composite (DSC) System
Technological Feasibility
Profiled DSC System
Technological Feasibility Economical
Merit Merit Merit Merit Merit Merit
6 4 3 8 5 5
8 8 - 7 7 -
5 4 5 6 3 6
8 3 2 7 4 3
6 2 5 7 4 5
8 3 4 8 5 5
8 7 7 8 7 7
5 7 3 6 7 4
8 8 7 10 5 8
Description
- Cellular deep deck composite with concrete slab to form long-span
floor system.
- Use of lightweight concrete would allow for long spans without use of
shoring
- Use of deck profile will help in reducing self weight of system, as
compared to DSC system
- 30 ft span was designed for
Deep Deck Composite System
Design Process
- Must consider both construction and composite phase in design
- SDI recommendations were used with some slight modifications to
account for long span
- RC theory used in analyzing composite section
- Floor vibrations analyzed using AISC DG 11 recommendations
- Calculations assumed contribution from adjoining bays would
participate
- Fire resistance may be enhanced by increased depth of concrete
- Existing UL designs could likely be implemented for further protection
if needed
Deep Deck Composite System
Cross Sections
10"
ATTACHMENT
LOAD BEARING
REQ'D. (SHEAR STUDS)
WIDE FLANGE BEAM
Deep Deck Composite System
DISCUSSION
- 10 in. deep composite deep deck system has been presented with self weights
comparable to existing metal deck concrete systems
- System could be erected in a manner similar to current metal deck systems
- Existing deck profiles may need to be modified with embossments to ensure
better composite action
- Cost of using deep cellular decks, is this reasonable?
- Research committee felt strongly that a system of this nature could be
implemented as a long span system
- Ongoing studies relating to interaction between slab and steel deck
- Large-scale experiments are needed to validate for floor vibration, fire
resistance, serviceability and strength requirements
Deep Deck Composite System
Committee Ratings