The realisation of the projects:

"sine qua non" condition for the


absorption of the EU Funds
The equation of the development:
Before accession

Financial Know-how Projects


resources (Administrative and
technical capacity) N
e
e
d
s

f kh p N
The equation of the development:
After accession

Financial Know-how
resources Projects N
(Administrative and e
technical capacity)
e
d
s

F kh p N
What does it means "technical capacity" to realise
projects

Administration
Private sector

Appropriate legal framework Technical equipment


Technical know how Technical know-how
Managerial know how Necessary structures

Necessary human resources


Necessary administrative
structures
What should be done by the administration?

Define the project


Maturity

Plan its realisation


Manage all preparatory phases

Realise or supervise the realisation of the project


Execution

Approval/reception of the realised works

These are obligatory stages which if not taken into account


from the beginning will be revenged
FROM FINANCING DECISION TO PROJECT
COMPLETION

WHAT HAS TO BE DONE


WHEN (with which sequence)
HOW LONG IT WILL TAKE
MAIN PHASES
DURING THE LIFE OF AN INFRASTRUCTURE PROJECT

PREPARATORY DESIGN WORKS TENDER &


ACTIONS TENDERING & CONSTRUCTION PHASE
PHASE DESIGN PHASE
DESIGN
TENDER

STAGE I : WORKS
DEFINITION OF INITIAL STAGE OF
THE PROJECT DESIGN- TENDER CONSTRUCTION
PREPARATORY
STUDIES (5 TO 8 (18 TO 30 MONTHS)
NATIONAL/ MONTHS)
REGIONAL
PLANNING STAGE II:
APPROVALS PRELIMINARY DESIGN
AND EIA APPROVAL
DECISION FOR
REALISING THE STAGE III: 23 TO 38 MONTHS
PROJECTS FINAL DESIGN

BUDGETARY
APPROVALS STAGE IV:
FINAL DESIGN OF
SPECIAL WORKS LAND
STAGE V: TENDER
EXPROPRIATION
DOCUMENTS AND (7 TO 24 MONTHS)
8 TO 12 MONTHS LAND
EXPROPRIATION
DIAGRAM

20 TO 46 MONTHS
TOTAL : 51 TO 96 MONTHS i.e
4.2 TO 8.0 YEARS
FOCUS ON THE DESIGN
INDICATIVE TIME SCHEDULE OF DESIGN TENDERING AND DESIGN PHASE FOR A REGIONAL ROAD PROJECT
ESTIMATED MINIMUM, MEAN AND MAXIMUM DURATION

YEAR 1 YEAR 2 YEAR 3 YEAR 4


ACTIVITIES
MIN MEAN MAX 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48
3M
1. DESIGN TENDER PROCEDURE 6M
DESIGN 9M
TENDER 2. AWARD OF DESIGN TENDER - COMMENCEMENT 0.5M
1M
OF DESIGN CONTRACT 1.5M
3M
3. PREPARATORY STUDIES (STAGE I) 4.5M
6M
STAGE I 0.5M
4. APPROVAL OF STAGE I 1M
1.5M
3M
5. PRELIMINARY STUDY (STAGE II) 4.5M
6M
STAGE II 0.5M
6. APPROVAL OF STAGE II 1M
1.5M
4M
7. FINAL STUDY (STAGE III) 6M
8M
STAGE III 0.5M
8. APPROVAL OF STAGE III 1M
1.5M
2M
9. FINAL STUDY OF BRIDGES, CULVERTS,
3M
RETAINING WALLS (STAGE IV) 4M
STAGE IV 0.5M
10. APPROVAL OF STAGE IV 1M
1.5M
2M
11. LAND EXPROPRIATION DIAGRAMM - TENDER
3M
DOCUMENTS (STAGE V) 4M
STAGE V 0.5M
12. APPROVAL OF STAGE V 1M
1.5M
20M
TOTAL 33M
46M
DESIGN TENDER STAGE
SEQUENCE OF DESIGN STAGES AND APPROVALS FOR
DESIGN TENDER PREPARATION
A REGIONAL ROAD PROJECT
DESIGN TENDER PUBLICATION

RESPONSE TO DESIGN TENDER

EVALUATION OF TENDERS

DESIGNATION OF PREFERED
TENDERER

APPEAL PROCEDURES

AWARD OF DESIGN
CONTRACT

C D E
A B
3D STAGE OF
5TH STAGE OF
1ST STAGE OF DESIGN - DESIGN -
2ND STAGE OF DESIGN DESIGN -
PREPARATORY STUDIES AND FINAL DESIGN
PRELIMINARY DESIGN TENDER
PRELIMINARY ROAD
DOCUMENTS
ALLIGNMENT

ROAD FINAL
F PUBLICATION OF GEOMETRIC GENERAL
TERRAIN SURVEYING ENVIRONMENTAL IMPACT S DESIGN AND CONDITIONS
I E T
TRAFFIC ASSESSMENT ASSESSMENT ALLIGNMENT OF CONTRACT
R C STUDY H
STUDY
S O I
PRELIMINARY ENVIRONMENTAL T ROAD PRELIMINARY N R SPECIAL
APPRAISAL GEOMETRIC DESIGN D D CONDITIONS
ALLIGNMENT STUDY FINAL DRAINAGE OF CONTRACT
PREPARATORY GEOMETRIC
DESIGN AND ALLIGNMENT S
DESIGN A
T P
S S TECHNICAL
A P
PRELIMINARY DRIANAGE T GEOTECHNICAL T DRAWINGS
G ENVIRONMENTAL IMPACT DOCUMENTS R
DESIGN A STUDY A
APPROVAL OF PROJECT LOCATION E ASSESSMENT O
LOCATION OF JUNCTIONS G G
AND PRELIMINARY V
E E
ENVIRONMENTAL APPRAISAL SIGNAGE AND TECHNICAL A
A MARKING SPECS L
FINAL
PRELIMINARY GEOLOGICAL APPROVAL OF ENVIRONMENTAL
P A A
ASSESSMENT GEOLOGICAL STUDY IMPACT ASSESSMENT
P P P
ROAD EQUIPMENT PRICED BILL OF
R P DESIGN P QUANTITIES
O R R BREAKDOWN
V OF COST
INCEPTION DESIGN OF O O
A CULVERTS, BRIDGES AND V ENVIRONMENTAL V
L ESTABLISHMENT OF
RETAINING WALL DESIGN A ARCHITECTURE A
ENVIRONMENTAL TERMS AND IRRIGATION
L PLAN
L
LAND
EXPROPRIATION
PROGRAMME OF PROCEDURES
GEOTECHNICAL PRELIMINARY
DESIGN OF
TRAFFIC STUDY COST BENEFIT STUDY INVESTIGATIONS CULVERTS,
LAND
EXPROPRIATION
BRIDGES AND
DIAGRAM
RETAINING
WALLS

LIGHTING AND LAND EXPROPRIATION


E/M DESIGN PROCEDURES

RESPONSIBILITIES:

DELIVERABLES BY THE 4TH STAGE OF


DESIGNER - CONSULTANT DESIGN FINAL
DESIGN OF
SPECIAL
APPROVAL BY THE PROJECT STRUCTURES
FINAL DESIGN FOURTH STAGE
MANAGING AUTHORITY OF CULVERTS, APPROVAL
BRIDGES AND
RETAINING WALL
DESIGN
APPROVALS BY OTHER INITIATION OF
AUTHORITIES WORKS TENDER
DESIGN TENDER STAGE

DESIGN TENDER STAGE

DESIGN TENDER PREPARATION

DESIGN TENDER PUBLICATION

RESPONSE TO DESIGN TENDER

EVALUATION OF TENDERS

DESIGNATION OF PREFERED
TENDERER

APPEAL PROCEDURES

AWARD OF DESIGN
CONTRACT
1st AND 2nd STAGE : PREPARATORY STUDIES, PRELIMINARY DESIGN AND EIA
STUDY, EIA APPROVAL
AWARD OF DESIGN
CONTRACT

B C

1ST STAGE OF DESIGN -


2ND STAGE OF DESIGN
PREPARATORY STUDIES AND
PRELIMINARY DESIGN
PRELIMINARY ROAD
ALLIGNMENT
S
F PUBLICATION OF E
TERRAIN SURVEYING ENVIRONMENTAL IMPACT C
TRAFFIC ASSESSMENT I
R ASSESSMENT O
STUDY N
S
PRELIMINARY ENVIRONMENTAL T ROAD PRELIMINARY D
APPRAISAL GEOMETRIC DESIGN
PREPARATORY GEOMETRIC ALLIGNMENT STUDY
DESIGN AND ALLIGNMENT S
S
T T
PRELIMINARY DRIANAGE ENVIRONMENTAL IMPACT A
A
APPROVAL OF PROJECT DESIGN ASSESSMENT G
LOCATION OF JUNCTIONS G
LOCATION AND PRELIMINARY E E
ENVIRONMENTAL APPRAISAL
PRELIMINARY GEOLOGICAL FINAL
APPROVAL OF ENVIRONMENTAL
ASSESSMENT A IMPACT ASSESSMENT A
GEOLOGICAL STUDY
P P
P P
R R
INCEPTION DESIGN OF
O O
CULVERTS, BRIDGES AND ESTABLISHMENT OF
V V
RETAINING WALL DESIGN ENVIRONMENTAL TERMS
A A
L L
PROGRAMME OF
GEOTECHNICAL
TRAFFIC STUDY COST BENEFIT STUDY INVESTIGATIONS

RESPONSIBILITIES:

DELIVERABLES BY THE
DESIGNER - CONSULTANT

APPROVAL BY THE PROJECT


MANAGING AUTHORITY

APPROVALS BY OTHER
AUTHORITIES
3, 4TH AND 5TH STAGE : FINAL DESIGN, TENDER DOCUMENTS, LAND
EXPROPRIATION DIAGRAM

D E
3D STAGE OF DESIGN - 5TH STAGE OF
FINAL DESIGN DESIGN - TENDER
DOCUMENTS
ROAD FINAL
GEOMETRIC DESIGN GENERAL
AND ALLIGNMENT CONDITIONS OF
S
STUDY T CONTRACT
E
C H
I SPECIAL
O FINAL DRAINAGE
R CONDITIONS OF
N DESIGN
D CONTRACT A
D
P
GEOTECHNICAL TECHNICAL P
S STUDY S DRAWINGS R
T T DOCUMENTS O
A SIGNAGE AND A V
G MARKING G TECHNICAL SPECS A
E E L
ROAD EQUIPMENT PRICED BILL OF
DESIGN QUANTITIES
A A
BREAKDOWN OF
P P
ENVIRONMENTAL COST
P P
ARCHITECTURE
R R
AND IRRIGATION
O O
PLAN LAND EXPROPRIATION
V V
PROCEDURES
A A
PRELIMINARY L
L LAND
DESIGN OF
CULVERTS, EXPROPRIATION
BRIDGES AND DIAGRAM
RETAINING WALLS
LAND EXPROPRIATION
LIGHTING AND E/M PROCEDURES
DESIGN

RESPONSIBILITIES:

DELIVERABLES BY THE 4TH STAGE OF DESIGN


DESIGNER - CONSULTANT FINAL DESIGN OF
SPECIAL STRUCTURES
APPROVAL BY THE PROJECT
FINAL DESIGN OF
MANAGING AUTHORITY FOURTH STAGE
CULVERTS,
APPROVAL INITIATION OF WORKS
BRIDGES AND
APPROVALS BY OTHER TENDER
RETAINING WALL
AUTHORITIES
DESIGN
SUMMARY - CONCLUSIONS

The design procurement and design process phase


is a critical period for the success of the project and is an
integral part of the project pipeline
The time required for design phase and works
procurement must not be underestimated
The correct sequence of preparatory stages leads to better
and more effective projects who are realized on time