You are on page 1of 24

QA/QC DOCUMENTATIONS

PQR

Specific codes and/or engineering


societies are often the driving force
behind the development of a
company's WPS. A WPS is supported by
a Procedure Qualification Record (PQR
or WPQR). A PQR is a record of a test
weld performed and tested (more
rigorously) to ensure that the
procedure will produce a good weld.
PWPS
A preliminary/pre-qualified welding
procedure specification (PWPS) is a
document containing required variables
of the welding procedure which needs to
be qualified in order to create the
qualified welding procedure specification
(WPS).
Based on the customer's input on type
of material, dimensions and joint
configuration, the pWPS will be prepared
WPS
A Welding Procedure Specification
(WPS) is the formal written document
describing welding procedures, which
provides direction to the welder or
welding operators for making sound
and quality production welds as per the
code requirements . ... A WPS is
supported by a Procedure Qualification
Record (PQR or WPQR).
INITIAL WELDER EVALUATION

The document which used to mention


the acceptance and rejection of a weld
joint welded by a welder
WELDER QUALIFICATION TEST ATTENDENCE REQUISITION

Welder certification, (also known as


welder qualification) is a process which
examines and documents a welder's
capability to create welds of acceptable
quality following a well defined welding
procedure.
WQTAR contains the details regarding
wqt carried out
DAILY WELDING REPORT
It is report regarding the no of weld
joints completed in a day.
It contains the no of weld joints
completed by t welders including
area ,dw no, line no ,weld passes etc
FIT UP &WELD VISUAL INSPECTION REPORT

It is used to report the dimensional


details checked by the qc inspector like
root gap, bevel angle, root face and
visual inspection details
MATERIAL INSPECTION REPORT
The Material Inspection Receiving
Report provides you information about
incoming material inspection at the
shop and site. ... After the receiving
inspection, the material controller shall
prepare the Material Receiving Report.
NDE CLEARANCE
In order to determine the suitability of the
weldjoint for its intended purpose, some degree
of nondestructive examination/testing
(NDE/NDT) should be conducted as part of
sound fabrication practice and quality
assurance. For non-code fabrication, NDE may
be as simple as visual or liquid/dye penetrant
inspection. For code fabrication, certain
mandatory inspections may be required. These
NDE methods should be considered for both
intermediate inspections during multi-pass
welding, as well as for final acceptance of the
weldjoint.
NDE&HEAT TREATMENT REQUISITION FORM

Form which is used for requesting non


destructive inspection and heat
treatment process. Contains drawing
details and weld details
PRESSURE TEST REPORT
This form must be completed for each
section of newly installed section of
pipe or service line and on each service
line that is disconnected from the main
for any reason.
PUMP CHECK LIST
Chances are that your facility has
several pumps performing various
tasks. Pumps are necessary for the
smooth operation of your building
whether they are used for HVAC,
domestic water, or process. To keep
pumps running properly, it's prudent to
keep a regular maintenance schedule
using a pump maintenance checklist.
REQUEST FOR INSPECTION
There are several points during
construction where an inspection may
be required. ... When you have
completed a segment of your project
requiring that an inspection be
performed
WELDERS CONTROL SHEET BY RADIOGRAPHIC EXAMINATION

Radio graphic examination report is a


document which contains the details of
weld joints whether it can be accepted
or not ,any type of defects present in it.
TECHNICAL QUERY
Technical query is the formal process of
asking a clarification or a question from
the concerned departments involved in
the execution of the project. The
Technical query can be raised between
Owner & Contractor, between site
operations of the contractor and
engineering team of the contractor etc.
WELD REPAIR RECORD
Document which contains the details of
weld repairs with the support of ndt
report.
BLAST/PAINT RELEASE FORM
Document or release form which used
to hand over the work to the paint/blast
department for further action
PAINT INSPECTION REPORT
Inspection report which contains all the
find outs regarding a painting
FIELD INSPECTION REPORT
It is final inspection report otherwise
known as final punch/check list.it
contains the unfinished or balance work
which has to be done before handover
FLANGE MANAGEMENT CERTIFICATE

Punch list or check list regarding a


flange.
HAND OVER CERTIFICATE
Certificate which used to hand over the
work done by the contractor to the
client.
THANKS

You might also like